Start date of planned outage End date of planned outageImpact (i.e. capacity day/restriction)
23rd February 2023 05:00to23rd February 2023 17:001/2 Capacity Day (Cancelled 09/02/23)
27th April 2023 05:00to27th April 2023 17:001/2 Capacity Day
18th May 2023 05:00to18th May 2023 17:001/2 Capacity Day (moved from 11/05/23)
25th May 2023to25th May 2023Full Capacity Day (Cancelled 12/05/23)
8th June 2023 05:00to8th June 2023 17:001/2 Capacity Day (Cancelled 31/05/23)
15th June 2023to15th June 2023Full Capacity Day
4th July 2023 05:00to4th July 2023 17:001/2 Capacity Day (moved from 06/07/23)
13th July 2023 05:00to13th July 2023 17:001/2 Capacity Day
20th July 2023 05:00to20th July 2023 17:001/2 Capacity Day
10th August 2023 05:00to10th August 2023 17:001/2 Capacity Day
16th August 2023to16th August 2023Full Capacity Day (Cancelled 31/05/23)
17th August 2023 05:00to17th August 2023 17:001/2 Capacity Day (Cancelled 31/05/23)
14th September 2023 05:00to14th September 2023 17:001/2 Capacity Day
5th October 2023 05:00to5th October 2023 17:001/2 Capacity Day (Confirmed on 18/09/23)
23rd November 2023 05:00to23rd November 2023 12:00Maintenance works being carried out.
95 GWh restriction, 157 GWh available

Update as at 11:40am:
Maintenance work complete
61 GWh restriction, 191 GWh available
 