Planned Maintenance 2019

 2019 PLANNED MAINTENANCE
 
30th April 2019 to 30th April 2019 1/2 Capacity Day
23rd May 2019 to 23rd May 2019 1/2 Capacity Day
11th June 2019 to 11th June 2019 30.50 GWh
12th June 2019 to 12th June 2019 30.50 GWh
23th July 2019 to 23th July 2019 1/2 Capacity Day
30th July 2019 to 30th July 2019 1/2 Capacity Day
14th August 2019 to 14th August 2019 1/2 Capacity Day
22nd August 2019 to 22nd August 2019 1/2 Capacity Day
00:01
23rd September 2019
to 23:59
23rd September 2019
Full Capacity Day
(Spread over two gas days)
00:01 29th October 2019 to 11:59 30th October 2019 Full Capacity Day + 1/2 Capacity Day
(Spread over two gas days)
Confirmed