2018 PLANNED MAINTENANCE
Start date of planned outage |
End date of planned outage |
Impact (i.e. capacity day/restriction) |
|
8th May 2018 | to | 8th May 2018 | 52.69 GWh |
9th May 2018 | to | 9th May 2018 | 200.21 GWh |
3rd July 2018 | to | 3rd July 2018 | 52.69 GWh |
4th July 2018 | to | 4th July 2018 | 200.21 GWh |
1st August 2018 | to | 1st August 2018 | 1/2 capacity day |
7th August 2018 | to | 7th August 2018 | 1/2 capacity day |
14th August 2018 | to | 14th August 2018 | Full capacity day |
15th August 2018 | to | 15th August 2018 | 1/2 capacity day |
Whilst every effort is made to ensure that the information is given in good faith and to the best of Dragon LNG Limited’s knowledge and belief at the time of posting, no warranty is given as to the accuracy or completeness of the information.