NOTIFICATION OF PLANNED MAINTENANCE
 2020 PLANNED MAINTENANCE

Start date of planned outage

End date of planned outage

Impact (i.e. capacity day/restriction)

05:00
16th January 2020
to 17:00
16th January 2020
1/2 Capacity Day
Cancelled
05:00
29th April 2020
to 17:00
29th April 2020
1/2 Capacity Day
Confirmed
6th May 2020 to 6th May 2020 1/2 Capacity Day
7th May 2020 to 7th May 2020 1/2 Capacity Day
Cancelled
18th May 2020 to 18th May 2020 1/2 Capacity Day
Cancelled
26th May 2020 to 26th May 2020 1/2 Capacity Day
Cancelled
28th May 2020 to 28th May 2020 1/2 Capacity Day
(Amended to 18th May 2020)
17th June 2020 to 17th June 2020 Full Capacity Day
14th July 2020 to 14th July 2020 1/2 Capacity Day
21st July 2020 to 21st July 2020 Full Capacity Day
13th August 2020 to 13th August 2020 1/2 Capacity Day
Cancelled
20th August 2020 20th August 2020 Full Capacity Day
25th August 2020 25th August 2020 Full Capacity Day
05:00
17th September 2020
to 17:00
17th September 2020
1/2 Capacity Day
Unconfirmed (Planned  but subject to change)

2021 Planned Maintenance

17th May 2021 to 11th June 2021 Full Capacity Days
(26 days in total)
Whilst every effort is made to ensure that the information is given in good faith and to the best of Dragon LNG Limited’s knowledge and belief at the time of posting, no warranty is given as to the accuracy or completeness of the information.