NOTIFICATION OF PLANNED MAINTENANCE
 2019/2020 PLANNED MAINTENANCE

Start date of planned outage

End date of planned outage

Impact (i.e. capacity day/restriction)

30th April 2019

to 30th April 2019 1/2 Capacity Day
23rd May 2019 to 23rd May 2019 1/2 Capacity Day

11th June 2019

to 11th June 2019 30.50 GWh

12th June 2019

to 12th June 2019 30.50 GWh

23th July 2019

to 23th July 2019 1/2 Capacity Day

30th July 2019

to 30th July 2019 1/2 Capacity Day

14th August 2019

to 14th August 2019 1/2 Capacity Day

22nd August 2019

to 22nd August 2019 1/2 Capacity Day

00:01
23rd September 2019

to 23:59
23rd September 2019
Full Capacity Day
(Spread over two gas days)

00:01
29th October 2019

to

11:59
30th October 2019

Full Capacity Day + 1/2 Capacity Day
(Spread over two gas days)
Confirmed

6th May 2020

to 6th May 2020 1/2 Capacity Day
7th May 2020 to 7th May 2020 1/2 Capacity Day

26th May 2020

to 26th May 2020 1/2 Capacity Day

28th May 2020

to 28th May 2020 1/2 Capacity Day

17th June 2020

to 17th June 2020 Full Capacity Day

14th July 2020

to 14th July 2020 1/2 Capacity Day

21st July 2020

to 21st July 2020 Full Capacity Day

13th August 2020

to 13th August 2020 1/2 Capacity Day

20th August 2020

20th August 2020 Full Capacity Day

25th August 2020

25th August 2020 Full Capacity Day
Whilst every effort is made to ensure that the information is given in good faith and to the best of Dragon LNG Limited’s knowledge and belief at the time of posting, no warranty is given as to the accuracy or completeness of the information.